Total U.S LNG feedgas demand soared to 15.73 Bcf/d last week, up 0.51 Bcf/d from the previous week – once again driven by the newest rising star – Plaquemines LNG.

Plaquemines' owner, Venture Global, received approval to commission a temporary gas turbine generator on March 10 and also to commission two additional gas turbine generators from phase two of the LNG project on March 20. As a result, feedgas intake at the terminal began rising on March 13 and has been above 2 Bcf/d since March 19 (see chart below). The first nine of 18 liquefaction blocks - all of which are from Phase 1 of the project are commissioning and taking feedgas.

The other U.S. terminals experienced minor changes in feedgas intake last week. Sabine Pass, Calcasieu Pass, Cove Point, and Cameron are operating above contracted utilization levels. Freeport is operating at full capacity, while Corpus Christi and Elba are at about 85% capacity. 

Cheniere conducted pipeline maintenance on the Corpus Christi pipeline from March 18 to March 23, which reduced feedgas to the terminal.

Thanks to the high level of activity at Plaquemines, the terminal has consistently exported two to three cargoes each week and has exported 10 so far this month – which is already higher than its total exports in February. Plaquemines has given the U.S. LNG industry high hopes, but as we’ve discussed, the commissioning process typically has many ups and downs. Check out our LNG Voyager for more details.

Create a FREE Account to Read Full Article