Bat Out of Hell - Bat-related Delay in Rover Pipeline A Godsend for Canadian Gas?

Author Housley Carr

The build-out of incremental natural gas takeaway capacity out of the Marcellus/Utica region has come in fits and starts, with new pipelines—as opposed to the reversal or expansion of existing pipes—proving to be the most troublesome. Energy Transfer Partners and Traverse Midstream Holdings’ long-planned 3.25-Bcf/d Rover Pipeline to southern Michigan is a case in point. The latest challenge for the $4.2 billion project is getting final federal approval in time to allow tree clearing along the pipeline’s 711-mile route to be completed before federally protected bats start roosting in early April. If that timeline’s not met, Rover’s planned completion later in 2017 may be delayed a full year, enabling Western Canadian gas producers to sell more gas to Ontario and the Upper Midwest. Today we assess what’s at stake for ETP, Traverse, and producer-shippers in the Marcellus/Utica and Western Canada.