The largest producer of LNG for export from the U.S., Cheniere Energy, gave an update on its project completion timeline during its latest earnings call. The timeline is largely the same as was presented in its Q2 earnings call. The original Corpus Christi Stage 3 project is now substantially complete, with the last train finished in mid-August. Midscale Trains 8 and 9 are now 59% complete and are still expected to reach substantial completion in the second half of 2028. The company reports that further expansions at Sabine Pass and Corpus Christi are still on track to reach FID, with an FID target of late 2026 or early 2027 for Sabine Pass and late 2027 to early 2028 for Corpus Christi. 