U.S. LNG feedgas rebounded last week as Freeport returned to full operations following an unplanned outage. Feedgas averaged 19.8 Bcf/d (blue dotted line below) for the week ending November 8, up almost 0.5 Bcf/d week-on-week.

Freeport tripped offline on October 26 due to an interruption in the power feed, and it restarted the next day but didn’t return to full capacity. Then, on November 1, Train 2 was taken offline for maintenance work. Feeport returned to full operations last weekend, according to our LNG Voyager weekly report.

Intake at the commissioning Golden Pass averaged 0.8 Bcf/d last week and has been above 0.7 Bcf/d for two weeks. All U.S. terminals are operating at full contracted capacity or peak levels, with intake at Plaquemines, Calcasieu Pass and Cove Point particularly strong.