Status
Commodity
NGLs
Operator
Kinder Morgan
Stage
Cancelled
Products
Y-Grade
Project Type
Combination
In Service Date
Q4 2018
Metrics
Diameter
26 Inches
Base Capacity
150 Mb/d
Expansion Capacity
280 Mb/d
Total Capacity
430 Mb/d
The will require the abandonment and conversion of 964 miles of natural gas service on TGP, the construction of approximately 200 miles of new pipeline from Louisiana to Texas, and new storage capacity and laterals in Ohio.
Project not listed in backlog of planned pipeline projects in Kinder Morgan's January 2016 investor presentation.
Current status is unclear, no mention of the project in KMI's 8/2018 Investor Presentation
Officially cancelled 10/2018