Northeast Energy Direct

Operator: 

Tennessee Gas

Commodity: 

Natural Gas

Stage: 

Cancelled

Project Type: 

Combination

In Service Date: 

Q4/2018

Diameter: 

30 inches

Length: 

188 miles

Est Capital Cost: 

$ 3,300 Million

Expansion Capacity: 

1,200 MMcf/d

Total Capacity: 

1,200 MMcf/d

Origin: 

Upstate, NY
United States
PADD 2

Destination: 

Middlesex County, MA
United States
PADD 1

On April 20th, 2016 Kinder Morgan announced that they were suspending the project citing lack of additional commitments from shippers effectively cancelling the pipeline.

Tags: