Operator:Tennessee Gas Commodity:Natural Gas Stage:Cancelled Project Type:Combination |
In Service Date:Q4/2018 Diameter:30 inches Length:188 miles Est Capital Cost:$ 3,300 Million |
Expansion Capacity:1,200 MMcf/d Total Capacity:1,200 MMcf/d |
Origin:Upstate, NY
United StatesPADD 2 Destination:Middlesex County, MA
United StatesPADD 1 |
On April 20th, 2016 Kinder Morgan announced that they were suspending the project citing lack of additional commitments from shippers effectively cancelling the pipeline.