Operator:Energy Transfer Commodity:Crude Oil Stage:Operational Project Type:Combination |
In Service Date:Q2/2017 Diameter:30 inches Length:744 miles Est Capital Cost:$ 1,000 Million |
Base Capacity:360 Mb/d Expansion Capacity:210 Mb/d Total Capacity:570 Mb/d |
Origin:Patoka, IL
United StatesPADD 2 Destination:Nederland, TX
United StatesPADD 3 |
Expandable to 570 Mb/d, P66 25% JVP
Will be the southern transport leg of the Dakota Access Pipeline (DAPL).
Start up date pushed back to 2Q 2017 to accommodate DAPL delay.