Utica Marcellus Texas Pipeline

Operator: 

Kinder Morgan

Commodity: 

NGLs

Stage: 

Cancelled

Project Type: 

Combination

In Service Date: 

Q4/2018

Diameter: 

26 inches

Length: 

1,164 miles

Est Capital Cost: 

$ 4,000 Million

Products: 

Y-grade

Expansion Capacity: 

430 Mb/d

Total Capacity: 

430 Mb/d

Origin: 

Mercer, PA
United States
PADD 1

Destination: 

Mont Belvieu, TX
United States
PADD 3

The will require the abandonment and conversion of 964 miles of natural gas service on TGP, the construction of approximately 200 miles of new pipeline from Louisiana to Texas, and new storage capacity and laterals in Ohio.
Project not listed in backlog of planned pipeline projects in Kinder Morgan's January 2016 investor presentation.

Current status is unclear, no mention of the project in KMI's 8/2018 Investor Presentation

Officially cancelled 10/2018